H100, H200, B200, GB200 and GB300 side by side: power per GPU, system and rack, how each is cooled and what the rack weighs. Use it to check a site before you sign.
LD Advisors · Updated October 25, 2026
| Platform | Power per GPU | Power per system | Power per rack | Cooling and weight |
|---|---|---|---|---|
| H100 (HGX/DGX) | 700 W | 10.2 kW per 8-GPU system | About 41 kW with four systems in an air-cooled rack (NVIDIA). Up to about 70 kW with rear-door cooling (Dell). | Air or rear-door. About 288 lb per system. |
| H200 (HGX) | 700 W | 10.2 kW | Same as H100 | Same chassis as H100 |
| B200 (HGX/DGX) | Up to 1,000 W | 14.3 kW | About 55 kW air-cooled (GIGABYTE). About 103 to 107 kW with direct liquid cooling (GIGABYTE, Dell). | Air or direct-to-chip |
| GB200 NVL72 | About 1,200 W (estimate) | One 72-GPU rack | About 120 to 132 kW nominal. HPE lists an estimated peak of about 192 kW. | Direct-to-chip hybrid: about 115 kW to liquid and 17 kW to air (QCT). About 3,245 lb. |
| GB300 NVL72 | About 1,400 W (estimate) | One 72-GPU rack | 132 kW nominal and about 155 kW peak. HPE recommends 192 kW of busway. | Direct-to-chip. About 3,300 lb. An in-row 1.3 MW CDU serves up to eight racks (HPE). |
Sources: HPE GB300 NVL72 QuickSpecs; HPE GB200 NVL72 QuickSpecs; NVIDIA DGX documentation; Dell; GIGABYTE; QCT; Vertiv; SemiAnalysis (per-GPU estimates for NVL72). Figures vary by vendor and configuration, so confirm with your hardware vendor. GB300 guide → · Requirement template →
We'll come back the same business day. Details stay under NDA, and we can take your requirement to operators anonymously.
Have capacity to fill? List your capacity
Got it. Your requirement is in.
We'll reply the same business day. If you'd like an NDA in place first, say so in your reply and we'll send ours.
That didn't go through. Email contact@ldadvisors.ai and we'll pick it up from there.